What's happening? |
|
|||
|
|
|
||||
|
2nd February 2014 |
First 5 yearly architect’s report
– Jonathan Gotelee (Architect) |
||||
|
6th August 2009 |
Final accounts agreed with EWHT |
||||
|
6th February 2009 |
Final meeting on site with Iain
Abbot (Architect) & Alastair Shields (Wm Black & Sons Ltd – main
contractor) |
||||
|
14th September 2008 |
Defect liability period ends |
||||
|
19th September 2007 |
Practical completion |
||||
|
19th January 2007 |
Reslating complete. Lead roof complete. Both still need snagging.
Garden wall 60% complete. Work approx 5 weeks
behind programme. |
||||
|
12th January 2007 |
Reslating to rear roof 80%. Reslating to
Wellington Street roof 70%. Work estimated at 5 weeks behind programme. |
||||
|
15th December 2006 |
Trouble with miscreants on roof on
14th December. Poor weather has also been delaying progress. Lead roofing 90%
complete. Garden wall rebuilding 40%. |
||||
|
8th December 2006 |
Roof protection scaffold being
removed. |
||||
|
1st December 2006 |
Lead cover flashings in progress.
New stone dentils complete. |
||||
|
24th November 2006 |
Lead roofing 80% complete. New
cupola installed - painting in progress. Attic insulation and access boarding
complete. New dentils on Hillside Crescent elevation commenced. Final fixing
of new windows in progress. |
||||
|
17th November 2006 |
Lead roofing 70% complete. New
cupola in progress. Rebuilding of rear garden wall 25% complete. |
||||
|
14th November 2006 |
Last
contribution from neighbours (69th) received - £134,835.00 collected |
||||
|
10th November 2006 |
Stone replacement on upper floors
of Hillside Crescent elevation complete. Rebuilding of garden wall in
progress. |
||||
|
3rd November 2006 |
Leadwork on roof in progress.
Dentils on Hillside Crescent elevation removed. Window replacements in
progress. |
||||
|
30th October 2006 |
Plywood covering to existing roof
80%. Attic roof insulation 75% and access boarding in place. Stone
replacement continuing on Hillside Crescent elevation. |
||||
|
13th October 2006 |
Reslating to rear roof 50%. Reslating
Wellington Street roof 50%. Roof scaffold complete. Attic space cleared and
cleaned. |
||||
|
6th October 2006 |
Stone replacement on Wellington
street elevation in progress. Cupola removed and awaiting replacement.
Unstable north end of west garden wall dismantled and ivy removed. Tranch 2 of tree work now completed. Foundations poured
for rebuilding garden wall. Roof scaffold 4 weeks behind programme, though it
is hoped that the lead work contractor will be able to complete in less time
than scheduled so the slippage can be recovered. |
||||
|
28th September 2006 |
Dummy windows on wellington Street
all replaced. Stone replacement work on rear elevation all complete.
Repointing work on rear elevation in progress. Roof protection scaffold in
progress. Opening up fireplaces in individual flats in progress. Works
generally on programme. Window works & replacements to begin next week. |
||||
|
14th September 2006 |
Tranch 1 of the tree works on the back greens took place on
Monday 11th. One of the ash trees and the elder on 10 Wellington Street's
green were removed and the rowan on 28 Wellington Street's green was pruned.
The tree surgeons will be returning on October 2nd to remove the other ash at
10 Wellington Street, prune the ash on 24 Hillside Crescent's green and
remove three other small scrappy trees. Meanwhile, the contractors will be
able to get started with laying foundations and rebuilding some of the garden
walls. |
||||
|
7th September 2006 |
Chimney 4
complete. That was the last one, so now
all the chimneys have been completely rebuilt. Reslating
on the Hillside Crescent elevation is complete, and the rear roof is 25%
complete. Works are generally on programme. |
||||
|
24th August 2006 |
Chimney 4 nearing completion. All
other chimneys now complete! Slate stripping on front roof pitch now
complete. Slate dressing and sizing in progress. Lead flashings in progress. |
||||
|
18th August 2006 |
Stair rep Chris Perring met with
Alastair Shields, MD of Blacks, Brian Miller, Site Foreman and Iain Abbot,
architect for a progress report and and inspection
of progress on the building. |
||||
|
3rd August 2006 |
Chimney 4 dismantled. Tree surgeons
apponted - Frontier Forestry. Timber treatment
contractor appointed. |
||||
|
27th July 2006 |
Chimney 2 complete. Chimney 3 50%
rebuilt. New chimney cans on site. Cast iron work on front elevation in progerss. |
||||
|
20th July 2006 |
Chimney 2 50% rebuilt. Chimney 3
dismantled. |
||||
|
14th July 2006 |
Chimneys 5 & 9 complete.
Chimneys 10 & 1 rebuilt to underside of cope. Chimney 2 dismantled.. Chimney 4 scaffolded -
awaiting closing of fireplaces. Repointing on rear elevation 90% complete. Cast
iron pipework on rear 95% complete. Window mastic being raked out prior to
replacement. Pitched roofs at front and rear - slate stripping in progress.. |
||||
|
15th June 2006 |
Rafter ends exposed along Hillside
Crescent & Wellington Street for inspection. Cutting out string course
stones on elevations and window sills continuing. Infilling around new
drainage pipework to rear elevation in progress. |
||||
|
12th June 2006 |
Structural engineer's report on
roof with relation to extra load from new leadwork, cornice stones, chimney
rebuilding progress and window lintels on ground floor. All appears
satisfactory. I have a copy of the full report if anyone wants to see it. |
||||
|
9th June 2006 |
Stair rep Chris Perring met with
Alastair Shields, MD of Blacks, Brian Miller, Site Foreman and Iain Abbot,
architect for a progress report and and inspection
of progress on the building. (click here to see pictures) |
||||
|
8th June 2006 |
Having received a report from a tree
specialist about the trees on the back green, the contractors have now been
instructed to obtain quotes per the specialist's recommendations. Also
instructed to obtain quotes for a full precautionary timber survey. |
||||
|
1st June 2006 |
Chimney 9 dismantled - no stone
re-usable. Chimney 8 - cope in place, cans in progress. Chimney 7 - cope 75%
complete. Chimney 6 - cope in progress. Chimney 5 - dismantled. Slate
stripping commenced. Infilling around new drainage on rear in progress.
Architect has instructed replacement of string course dentils. (click here to see pictures) |
||||
|
18th May 2006 |
External drainage on rear
elevation 70% complete. Preparing to dismantle Chimney 5 (blocking flues etc) |
||||
|
4th May 2006 |
New external drainage pipework on
rear of building 40% complete. New chimney cans on order. |
||||
|
27th April 2006 |
Rebuilding of chimneys 6, 7 &
8 in progress - 50% complete. Scaffolding at rear complete. |
||||
|
20th April 2006 |
Stone for chimneys 6, 7 & 8
being cut in contractors yard. Scaffolding on rear
elevation in progress. |
||||
|
9th April 2006 |
3 most precarious chimneys
dismantled (shown in 2nd picture from right above) and now ready for rebuilding.
The stone which was removed was apparently VERY crumbly so these chimneys did
need urgent attention. (click
here to see pictures) |
||||
|
19th March 2006 |
Scaffolding now nearly complete on
East and South elevations. Precarious North garden wall dismantled for safety
and rubble from collapsed East wall tidied up. (click here to
see pictures) |
||||
|
27th February 2006 |
Contractors on site - Scaffolding
starts to go up. (click
here to see pictures) |
||||
|
|
|
||||
|
1st February 2006 |
Wm
Black & Sons Ltd appointed as main contractors |
||||
|
22nd December 2005 |
Formal
offer of Grant from EWHT |
||||
|
22nd August 2005 |
EWHT
approval to proceed to tender |
||||
|
13th May 2005 |
First
cheque into joint bank account |
||||
|
17th March 2005 |
Garden
wall fell down |
||||
|
February 2005 |
Notification
from EWHT that funds will be available 2005-06 and 2006-07 |
||||
|
16th April 2003 |
Agreement
in principle to offer a grant from EWHT |
||||
|
February 2003 |
Legal
agreement between all owners |
||||
|
21st June 2002 |
Detailed
survey of the building (Report received 09/08/2002) |
||||
|
4th February 2002 |
Meeting
of proprietors with EWHT at their offices |
||||
|
11th October 2001 |
Architect
& Trevor Harding (roofer) inspected chimneys in a cherry picker |
||||
|
25th May 2001 |
Initial
schedule of repairs issued by Iain Abbot & McLeod & Aitken (Q.S.) |
||||
|
1st May 2001 |
Appointed
Iain Abbot (architect) to prepare initial report |
||||
|
18th October 2000 |
EWHT
Initial inspection |
||||
|
5th September 2000 |
Application
form submitted to Edinburgh World Heritage Trust |
||||
|
17th May 2000 |
Report
on chimneys from Ian Moir - Civil Engineer |
||||
|
|
|
|
|||